Belgrade-Zrenjanin-Novi Sad highway - What is being planned on a route over 100 kilometer long?
The project involves the construction of a complete profile of the highway, between Ovca and Zrenjanin (Section 1 - length 67.67 km) and Zrenjanin and Novi Sad (Section 2 - length 35.75 km), with all necessary road facilities and level crossings, as well as about two kilometers expressways through Novi Sad. The construction of an alternative road route Zabalj Novi Sad is also planned, according to the Novi Sad Architectural and Construction Institute, in charge of the project organization.
As part of the highway route, following ring roads have been designed: Petlja Ovca, Petlja Glogonj/Jabuka, Petalja Kovačica, Petalja Orlovat, Petlja Ečka, Petalja Zrenjanin zapad, Petalja Zabalj.
Two parking lots and two rest areas are planned along the route.
Together with the highway route, adjacent facilities were also designed, i.e. constructions on interchanges (overpasses), bridges in the trunk of the highway, overpasses, culverts and passages for minor local roads, overpasses for the crossing of state roads.
As for the larger bridges, two bridges over the Tamis River, one bridge over the Tisa River, and a bridge over the Begei River stand out.
Highway in numbers
The total length of the highway is 103.42 km
Total length of the expressway: 1.99 km
Total length of the alternative road Zabalj-Novi Sad: 25.35 km
Basic characteristics of the highway route:
calculated speed: Vr=130 km/h
highway lane width: 3.75 m
width of the stop lane: 2.50 m
bank width: 2 m
width of dividing belt: 4 m
Most Important News
26.10.2024. | Construction, Transport
Serbia has project for reconstruction of rail section from Belgrade to Sid – Waiting for Croatia’s response
25.10.2024. | Agriculture, Industry, Construction, Transport, Finance
What is to be built on over 250 ha near Dobanovci? – Chinese Minth enters ownership of land planned for construction of Singidunum megacomplex
25.10.2024. | Agriculture, Industry, Construction, Transport, Finance
23.10.2024. | Construction, Transport
Construction of first highway through Banat starts from other direction too – Construction site for future traffic route to Belgrade opened in Zrenjanin
23.10.2024. | Construction, Transport
24.11.2024. | Finance
Serbia expecting decision on joining Single Euro Payments Area in December
24.11.2024. | Finance
03.12.2022. | IT, Telecommunications
In what way is digital marketing developing? – We will never create a formula for a perfect commercial
03.12.2022. | IT, Telecommunications
22.11.2024. | Finance
One of the longest bankruptcy proceedings in Serbia, the shutting down of Jugobanka, coming to a close
22.11.2024. | Finance