More Electricity to Come from South Banat – WV International Planning Construction of Samos Wind Farm of 900 MW Between Alibunar and Kovacica
![](/uploads/images/v5/lnSep.png)
![](/uploads/images/v5/lnSep.png)
![Illustration](https://www.ekapija.com/thumbs169/vetrenjaca_1_040322_tw1024.jpg)
The area covered by the plan amounts to 174.28 km2, and in the territory of the municipality of Alibunar, it encompasses parts of the cadaster municipalities: Dobrica, Ilandza, Novi Kozjak and Seleus, whereas in the territory of the municipality of Kovacica, it encompasses parts of the cadaster municipalities: Kovacica, Padina, Samos and Uzdin.
The construction is planned in two stages.
In the first stage, the plan is to realize the wind farm Samos 1 with a planned minimum power of 420 MW, whereas in the second stage, the plan is to realize the wind farm Samos 2 with a planned minimum installed power of 468 MW. The maximum height, the total height of the wind generators, will be around 250 m.
The spatial plan was prepared by the Public Enterprise for Spatial and Urban Planning “Institute of Urban Planning of Vojvodina” from Novi Sad, and the early public inspection will last until January 29.
I. Z.
![Pokrajinski sekretarijat za urbanizam i zaštitu životne sredine Novi Sad](/logo/165326_logo.gif)
![JP Zavod za urbanizam Vojvodine Novi Sad](/logo/36982_logo.gif)
![AAEC Energy Consulting doo Novi Sad](/logo/303291_logo.gif)
Naš izbor
Most Important News
07.05.2024. | IT, Telecommunications
Biggest Angular conference in the region – NG Belgrade Conf 2024
![](https://www.ekapija.com/thumbs169/ng_belgrade_conf_2024_1_070524_tw630.jpg)
06.05.2024. | Healthcare
Medical doctors and engineers from Nis design instrument which accelerates and improves efficiency of operating procedures – Negotiating with foreign companies about production
![](https://www.ekapija.com/thumbs169/operacija_070815_tw630.jpg)
06.05.2024. | Healthcare
06.05.2024. | Construction, Tourism, Sports, Culture, Healthcare
Sijarinska Banja should soon get a new look – Project documentation for reconstruction of rehabilitation center complex being prepared
![](https://www.ekapija.com/thumbs169/specijalna_bolnica_gejzer_sijarinska_banja_090323_tw630.jpg)
06.05.2024. | Construction, Tourism, Sports, Culture, Healthcare
03.07.2024. | Construction, Transport
High-speed Belgrade–Velika Plana railroad in additional investment package of European Commission of EUR 1.2 billion for Western Balkans
![](https://www.ekapija.com/thumbs169/evro_22_230120_tw630.jpg)
03.07.2024. | Construction, Transport
07.05.2024. | Industry, Construction
New Palfinger factory in Nis to start working in June
![](https://www.ekapija.com/thumbs169/palfinger_fabrika_nis_170523_tw630.jpg)
07.05.2024. | Industry, Construction
02.07.2024. | Energy, Industry
Local investor planning construction of two solar power plants near Arandjelovac
![](https://www.ekapija.com/thumbs169/solarna_elektrana_1_271023_tw630.jpg)
02.07.2024. | Energy, Industry